Gas Pipeline Phase 2
High-pressure gas pipeline installation over 10km
AI Insights for Gas Pipeline Phase 2
Loading AI insights...
Analyzing project data...
Start Date
2024-02-01
Status
Active
Completion
76.7%
Duration
days
Project Information
- Building Type:
- N/A
- Total SF:
- N/A
- Floor Count:
- N/A
- Location:
- Rural Pipeline Corridor
- Budget:
- $4,200,000
- End Date:
- 2024-11-30
Quick Actions
Project Activities
Add ActivityActivity | Type | Duration | Progress | Start Date | Crew Size | Actions |
---|---|---|---|---|---|---|
Pipeline Survey Sta 0-3000
Route survey and staking |
Other | 10 days |
|
2024-02-01 | 4 | |
Trenching Sta 0-1000
Excavate pipeline trench first section |
Sitework | 12 days |
|
2024-02-15 | 6 | |
Trenching Sta 1000-4000
Excavate pipeline trench middle section |
Sitework | 18 days |
|
2024-03-01 | 8 | |
Trenching Sta 4000-10000
Excavate pipeline trench final section |
Sitework | 25 days |
|
2024-03-15 | 10 | |
Pipe Install Sta 0-800
Install 24-inch steel pipe |
Other | 8 days |
|
2024-02-20 | 5 | |
Pipe Install Sta 800-3000
Install 24-inch steel pipe section 2 |
Other | 14 days |
|
2024-03-05 | 6 | |
Pipe Install Sta 3000-7000
Install 24-inch steel pipe section 3 |
Other | 20 days |
|
2024-03-20 | 8 | |
Backfill Sta 0-2000
Trench backfill and compaction |
Other | 10 days |
|
2024-03-01 | 4 | |
Site Restoration Sta 0-5000
Topsoil replacement and seeding |
Sitework | 15 days |
|
2024-04-01 | 6 |