Gas Pipeline Phase 2

High-pressure gas pipeline installation over 10km

AI Insights for Gas Pipeline Phase 2
Loading AI insights...

Analyzing project data...

Start Date

2024-02-01

Status

Active

Completion

76.7%

Duration

days

Project Information
Building Type:
N/A
Total SF:
N/A
Floor Count:
N/A
Location:
Rural Pipeline Corridor
Budget:
$4,200,000
End Date:
2024-11-30
Project Activities
Add Activity
Activity Type Duration Progress Start Date Crew Size Actions
Pipeline Survey Sta 0-3000
Route survey and staking
Other 10 days
100%
2024-02-01 4
Trenching Sta 0-1000
Excavate pipeline trench first section
Sitework 12 days
95%
2024-02-15 6
Trenching Sta 1000-4000
Excavate pipeline trench middle section
Sitework 18 days
80%
2024-03-01 8
Trenching Sta 4000-10000
Excavate pipeline trench final section
Sitework 25 days
50%
2024-03-15 10
Pipe Install Sta 0-800
Install 24-inch steel pipe
Other 8 days
100%
2024-02-20 5
Pipe Install Sta 800-3000
Install 24-inch steel pipe section 2
Other 14 days
85%
2024-03-05 6
Pipe Install Sta 3000-7000
Install 24-inch steel pipe section 3
Other 20 days
60%
2024-03-20 8
Backfill Sta 0-2000
Trench backfill and compaction
Other 10 days
90%
2024-03-01 4
Site Restoration Sta 0-5000
Topsoil replacement and seeding
Sitework 15 days
30%
2024-04-01 6
Project Documents
Upload Document
No Documents Uploaded

Upload project plans, BIM files, and other documents for AI processing.

Upload First Document