NC Museum of History - SOP Compliance Demo

Real-world schedule implementation following Carolinas Scheduling SOP

SOP Dashboard
Import Real-World SOP Example
NC Museum of History Renovation & Expansion

This project demonstrates complete SOP compliance using real schedule data from the NC Museum of History renovation project. The schedule includes:

  • Multi-phase bidding process (GMP #2 and #3)
  • Complex structural work with micro piles and FRP columns
  • Historic preservation requirements
  • SOP-compliant activity IDs (≤5 characters)
  • Duration compliance (≤15 days per activity)
  • 4D modeling requirements (multi-level structure)

$75M

Contract Value

2.6 Years

Project Duration

150K SF

Museum Space