Carolinas Scheduling SOP Compliance
5
Total Projects
0
Baseline Complete
0
Require 4D
0
Reports Generated
Project SOP Compliance Status
Project Name | Contract Value | Project Size | Float Status | Activity Compliance | 4D Status | Reports | Actions |
---|---|---|---|---|---|---|---|
Residential Towers Phase 1
Riverside Development
|
$0 | Unknown | Unknown |
|
Not Required | 0 | |
Industrial Warehouse
Industrial Park
|
$0 | Unknown | Unknown |
|
Not Required | 0 | |
Downtown Office Complex
Downtown District
|
$0 | Unknown | Unknown |
|
Not Required | 0 | |
Highway 101 Extension
Highway 101 Corridor
|
$0 | Unknown | Unknown |
|
Not Required | 0 | |
Gas Pipeline Phase 2
Rural Pipeline Corridor
|
$0 | Unknown | Unknown |
|
Not Required | 0 |
SOP Requirements Summary
Schedule Development Timelines
- DD Schedule: 2 weeks draft + 1 week review + 1 week finalize
- CD Schedule: 2 weeks update + 1 week review + 1 week finalize
- Baseline: 2 weeks with ops/sub feedback
Activity Requirements
- Activity IDs: Maximum 5 characters
- Duration: Maximum 15 days
- All dates populated (AS/AF or PS/PF)
Scheduler Assignment Rules
- Scheduler Required: Contract value > $10M
- Team Updates: Contract value ≤ $10M
- Senior Scheduler: 5-10 projects or 1-2 very large
4D Modeling Requirements
- Mandatory: All vertical projects > 2 levels
- 1 week to complete after initial P6 schedule
- Show structure through skin