Carolinas Scheduling SOP Compliance

5
Total Projects
0
Baseline Complete
0
Require 4D
0
Reports Generated
Project SOP Compliance Status
Project Name Contract Value Project Size Float Status Activity Compliance 4D Status Reports Actions
Residential Towers Phase 1
Riverside Development
$0 Unknown Unknown
0%
0/0 activities
Not Required 0
Industrial Warehouse
Industrial Park
$0 Unknown Unknown
0%
0/0 activities
Not Required 0
Downtown Office Complex
Downtown District
$0 Unknown Unknown
0%
0/0 activities
Not Required 0
Highway 101 Extension
Highway 101 Corridor
$0 Unknown Unknown
0%
0/0 activities
Not Required 0
Gas Pipeline Phase 2
Rural Pipeline Corridor
$0 Unknown Unknown
0%
0/0 activities
Not Required 0
SOP Requirements Summary
Schedule Development Timelines
  • DD Schedule: 2 weeks draft + 1 week review + 1 week finalize
  • CD Schedule: 2 weeks update + 1 week review + 1 week finalize
  • Baseline: 2 weeks with ops/sub feedback
Activity Requirements
  • Activity IDs: Maximum 5 characters
  • Duration: Maximum 15 days
  • All dates populated (AS/AF or PS/PF)
Scheduler Assignment Rules
  • Scheduler Required: Contract value > $10M
  • Team Updates: Contract value ≤ $10M
  • Senior Scheduler: 5-10 projects or 1-2 very large
4D Modeling Requirements
  • Mandatory: All vertical projects > 2 levels
  • 1 week to complete after initial P6 schedule
  • Show structure through skin