Industrial Warehouse

3-4 Week Lookahead Pull Planning Board

Back to Project
3-4 Week Lookahead Schedule (High Level Activities Only)
Week 1 Week 2 Week 3 Week 4
Steel Fab/Delivery
Steel Start
SOG Pours
MEP RIs
Deliveries
Inspections
Safety Activities
Preinstall Meetings
Deliveries
Material Delivery A
Equipment Delivery B
Safety Activities
Safety Training
Site Safety Review
Inspections
Foundation Inspection
Framing Inspection
Preinstallation Meetings
MEP Coordination
Steel Coordination
Milestone Board
NTP
Notice to Proceed
Foundation Complete
Major Milestone
Structure Complete
Major Milestone
Substantial Completion
Project Complete
SOP Requirements for Pull Planning
Format Requirements
  • Whiteboard format in conference room
  • 3-4 Week lookahead timeframe
  • High level activities only
  • Color coded organization
Content Requirements
  • Material deliveries
  • Preinstallation meetings
  • Inspections
  • Key safety activities
Note: Pull planning discussions are held during weekly subcontractor meetings. The CPM schedule and pull plan boards should match closely but not necessarily exactly, as pull plan boards are expected to have a greater level of detail.