Highway 101 Extension
New 5km highway extension with bridges, drainage, and paving
AI Insights for Highway 101 Extension
Loading AI insights...
Analyzing project data...
Start Date
2024-01-15
Status
Active
Completion
68.8%
Duration
days
Project Information
- Building Type:
- N/A
- Total SF:
- N/A
- Floor Count:
- N/A
- Location:
- Highway 101 Corridor
- Budget:
- $2,500,000
- End Date:
- 2024-12-31
Quick Actions
Project Activities
Add ActivityActivity | Type | Duration | Progress | Start Date | Crew Size | Actions |
---|---|---|---|---|---|---|
Site Clearing & Grubbing
Clear vegetation and remove stumps |
Sitework | 15 days |
|
2024-01-15 | 8 | |
Excavation Sta 0-1000
Cut and fill operations for first kilometer |
Sitework | 20 days |
|
2024-01-20 | 12 | |
Excavation Sta 1000-2500
Cut and fill operations middle section |
Sitework | 25 days |
|
2024-02-05 | 15 | |
Excavation Sta 2500-5000
Cut and fill operations final section |
Sitework | 30 days |
|
2024-02-20 | 18 | |
Drainage Install Sta 0-2000
Storm drainage system installation |
Other | 18 days |
|
2024-02-15 | 6 | |
Base Course Sta 0-1500
Granular base course placement |
Other | 12 days |
|
2024-03-10 | 10 | |
Drainage Install Sta 2000-5000
Storm drainage system final section |
Other | 22 days |
|
2024-03-01 | 8 | |
Asphalt Paving Sta 0-2500
Hot mix asphalt surface course |
Other | 16 days |
|
2024-04-01 | 8 |